Completed in 2017, the Highland Gate subdivision was one of our most demanding earthworks projects to date. The site was originally a golf course and was surrounded by hundreds of existing estate lots placing emphasis on competent dust mitigation and erosion control. A temporary Haul road and bridge was built through a protected wetland to facilitate site access. Over 100`000M3 was exported in 3 months in difficult ground conditions.
Location
Aurora, ON
Value
$3,500,000
Consultant
SCS Consulting Group
Owner
Geranium
Date
August, 2017
Category
Earthwork, Road Construction